— 1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Construction progress, complex updates and real estate investment news from Batumi
— 1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Installation of drywall profiles, on the 5th floor. Ongoing works. It creates a strong and stable base that forms the walls. 2. Ceramic block…
1. Facade works, the 15th -16th floors. This includes the installation of facade elements on balconies. The facade is being winterized. 2. Installation of…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works. - Painting of…
Due to adverse weather conditions, no other construction works are being carried out on the site today.
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Installation of drywall profiles, on the 5th floor. Ongoing works. It creates a strong and stable base that forms the walls. Buildings A, B…
1. Installation of drywall frames, the 9th floor. 2. Mockup construction on the 3rd, 13th floors. - Painting and wiring are ongoing on the 3rd floor. 3…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works. - Painting of…
— 1. Site access point preparation. Due to adverse weather conditions, no other construction works are being carried out on the site today.
1. Block C. Formwork removal from and installation for the stair flights It ensures precise shape and geometry of the staircase, supports the concrete during…
Building A 1. Installation of drywall profiles, on the 5th floor. Ongoing works. It creates a strong and stable base that forms the walls. 2. Ceramic block…
1. Facade works, the 12th – 13th floors. This includes the installation of facade elements on balconies. The facade is being winterized. 2. Installation of…
1. Plumbing. 2. Installation of ceramic granite tiles on the balconies of the units. Continued ceramic granite tiling work. 3. Finishing works. - Painting of…
— 1. Delivery of materials. Ceramic blocks and XPS insulation were unloaded. Due to adverse weather conditions, no other construction works are being carried…
1. Block C. Concrete pouring of staircases. 2. Block A. Completion of mockup installation. - Utilities system installation, namely: sewage, heating, and water…
Club. — Building A 1. Installation of drywall profiles, on the 5th floor. Ongoing works. It creates a strong and stable base that forms the walls. 2. Ceramic…
1. Facade works, the 12th – 13th floors. This includes the installation of facade elements on balconies. The facade is being winterized. 2. Installation of…
1. Plumbing and wiring. 2. Installation of ceramic granite tiles on the balconies and in the bathrooms of the units. Continued ceramic granite tiling work. 3…
1. Concreting of the floor slab, Villa 10 It ensures the better strength and stability, enhancing the structure durability. 2. Continuation of column formwork…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st