1. Block C. Pouring concrete for stair flights It is essential for creating a durable and robust foundation for the stairs. 2.Blocks A, B. Masonry work…
Construction progress, complex updates and real estate investment news from Batumi
1. Block C. Pouring concrete for stair flights It is essential for creating a durable and robust foundation for the stairs. 2.Blocks A, B. Masonry work…
Building A 1. Installation of drywall profiles, on the 4th floor. Ongoing works. It creates a strong and stable base that forms the walls. 2. Insulation of the…
1. Facade works, the 18th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. 2. Glazing of stained glass…
1. Plumbing. - Heating connection, monitoring of temporary heating. - Installation of drainage system on balconies on the 4th-5th floors. 2. Installation of…
1. Continuation of slab reinforcement, Villas 7-10 It strengthens the structure, enhancing durability and ensuring long-term stability. 2. Waterproofing of the…
1. Block С. Formwork removal from and installation for the staircases. It is necessary to create the precise shape and geometry of the staircase, support the…
Building A 1. Installation of drywall profiles, 3rd – 4th floors. Ongoing works. It creates a strong and stable base that forms the walls. 2. Insulation of the…
1. Facade works, the 18th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. The total area of the…
1. Plumbing. - Heating connection, monitoring of temporary heating. - Installation of drainage system on balconies on the 4th-5th floors. 2. Installation of…
—1. Continuation of slab reinforcement, Villas 7-10. It strengthens the structure, enhancing durability and ensuring long-term stability. 2. Waterproofing of…
1. Block С. Formwork removal from and installation for the staircases. It is necessary to create the precise shape and geometry of the staircase, support the…
Building A 1. Installation of drywall profiles, 3rd – 4th floors. Ongoing works. To create a strong and stable base that forms the walls. 2. Insulation of the…
1. Facade works, the 18th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. The total area of the…
1. Firefighting system installation. Installation of firefighting system. 2. Plumbing. - Commissioning of heating system. 3. Installation of ceramic granite…
1. Formwork installation for slabs, Villas 7-10 Installation of formwork to shape the slabs, essential for pouring concrete and forming the structure. 2…
1. Block С. Formwork removal from and installation for the staircases. It is necessary to create the precise shape and geometry of the staircase, support the…
Building A 1. Installation of drywall profiles, 2nd – 3rd floors. To create a strong and stable base that forms the walls. 2. Facade works. The facade works…
1. Facade works, the 17th – 19th floors. This includes the installation of facade elements on balconies. Facade is being winterized. 2. Glazing of stained glass…
1. Firefighting system installation. Installation of firefighting system. 2. Plumbing. - Commissioning of temporary heating system. 3. Installation of ceramic…
— 1. Formwork installation for slabs, Villas 7-10 Installation of formwork to shape the slabs, essential for pouring concrete and forming the structure. 2…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st