1. Блок С. Formwork removal from and installation for the staircases, in 2 townhouses. It is necessary to create the precise shape and geometry of the…
Construction progress, complex updates and real estate investment news from Batumi
1. Блок С. Formwork removal from and installation for the staircases, in 2 townhouses. It is necessary to create the precise shape and geometry of the…
Building A 1. Diamond drilling for engineering openings, the 1st floor. The layout and drilling are underway, it is necessary for future hotel utility…
1. Diamond drilling for engineering openings, the 16th , 19th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Installation of smoke extraction system. Construction of the smoke extraction shaft box. 2. Plumbing. Laying of heating mains in common areas. Installation…
Ceramic blocks were delivered. Due to unfavorable weather conditions the construction activities at the site are not being carried out today.
1. Formwork removal from and installation for the staircases. It is necessary to create the precise shape and geometry of the staircase, support the concrete…
Building A 1. Diamond drilling for engineering openings for downpipes. The layout and drilling are underway, necessary for future hotel utility installations…
1. Diamond drilling for engineering openings, the 18th - 20th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Heating system installation. 2. Facade works. Installing decorative…
1. Installation of sewer outlets, Villa 16. It is necessary to ensure proper connection of the drainage system and the functionality of the sewerage system. 2…
1. Ceramic block installation across the terrace. Blocks А, В, С. The ceramic blocks are being laid in accordance with the established standards. This process…
Building A 1. Diamond drilling for engineering openings for downpipes. The layout and drilling are underway, necessary for future hotel utility installations…
1. Diamond drilling for engineering openings, the 18th - 20th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Heating system installation. 2. Facade works. Installing decorative…
1. Continuation of staircase formwork installation, Villa 5. The formwork is installed to shape the staircase, enabling concrete pouring and the formation of…
1. Ceramic block installation across the terrace. Blocks А, В, С. The ceramic blocks are being laid in accordance with the established standards. This process…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, the 17th - 19th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Heating system installation. 2. Cladding ceramic granite in the…
1. Continuation of staircase formwork installation, Villas 3, 4, 5. The formwork is installed to shape the staircase, enabling concrete pouring and the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st