Block A 1. Facade work. Facade cladding with clinker tiles, on the roof. 2. Plastering work. Installation of decorative plaster on balconies. 3. Covering metal…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Facade work. Facade cladding with clinker tiles, on the roof. 2. Plastering work. Installation of decorative plaster on balconies. 3. Covering metal…
1. Installation of engineering systems. — Electrical work. — Plumbing work. — Sealing ventilation openings. 2. Plastering work. Installation of decorative…
1. Monolithic works. — Formwork installation for the staircase on the 2nd floor, villa 10. — Column installation, villa 12. 2. Installation of side panels for…
1. Block A. Installation of engineering systems. Electrical installation work, fastening clips, pulling electrical cables. 2. Block C. Installation of…
Block A 1. Facade work. Facade cladding with clinker tiles, on the roof. 2. Plastering work. Installation of decorative plaster on balconies. 3. Covering metal…
1. Installation of engineering systems. — Electrical work. — Plumbing work. 2. Plastering work. Installation of decorative plaster on balconies. 3. Ceiling…
1. Block A. Installation of engineering systems. — Electrical installation work. — Chasing walls for electrical cable laying. 2. Block E. Installation of…
Block A 1. Facade work. — Facade cladding with clinker tiles. — Facade insulation, XPS installation. 2. Plastering work. Installation of decorative plaster on…
1. Installation of engineering systems. — Electrical work. — Plumbing work. 2. Plastering work. Installation of decorative plaster on balconies. 3. Ceiling…
1. Monolithic works. — Formwork installation for the staircase on the 2nd floor, villa 10. — Column installation on the 2nd floor, villas 15–16. 2. Installation…
1. Block A. Installation of engineering systems. — Electrical installation work. — Wall channelling for electrical cable laying. 2. Block E. Installation of…
Block A 1. Facade work. — Facade cladding with clinker tiles. — Facade insulation, XPS installation. 2. Plastering work. Installation of decorative plaster on…
1. Installation of engineering systems. — Electrical work. — Plumbing work. 2. Plastering work. Installation of decorative plaster on balconies. 3. Ceiling…
1. Monolithic works. — Formwork installation for the staircase on the 2nd floor, villa 10. — Preparation of reinforcement for column installation. 2…
1. Block A. Installation of engineering systems. Electrical installation work, laying electrical cables. 2. Block E. Installation of engineering systems…
Block A 1. Facade work. — Facade cladding with clinker tiles. — Facade insulation, XPS installation. 2. Plastering work. Preparatory work for applying…
1. Installation of engineering systems. — Electrical work, 15th floor. — Plumbing work, 20th floor. 3. Plastering work. Installation of decorative plaster on…
1. Monolithic works. — Formwork installation for the staircase on the 2nd floor, villa 12. — Preparation of reinforcement for column installation. 2…
1. Block A. Installation of engineering systems. Electrical installation work, electrical cable laying. 2. Block E. Installation of engineering systems…
Block A 1. Facade work. Facade cladding with clinker tiles, grouting of tile joints. 2. Waterproofing work. Preparation of terraces for waterproofing. 3…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st