Block A 1. Finishing works. Laying porcelain stoneware on balconies. 2. Waterproofing works. Installation of coating waterproofing on balconies. 3. Plastering…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Finishing works. Laying porcelain stoneware on balconies. 2. Waterproofing works. Installation of coating waterproofing on balconies. 3. Plastering…
1. Installation of engineering systems. — Electrical work, installation of clips. — Plumbing work. — Installation of air conditioning system. 2. Plastering…
1. Installation of stained glass structures. Installation of stained glass windows in villa 1.
1. Block A. Installation of engineering systems. Electrical work, fastening clips, laying electrical cables. 2. Block A. Installation of plasterboard frame…
Block A 1. Finishing works. Laying porcelain stoneware on balconies. 2. Waterproofing works. Installation of coating waterproofing on balconies. Block B 1…
1. Installation of engineering systems. — Electrical work. — Installation of a fire extinguishing system. — Installation of air conditioning system. 2…
1. Monolithic works. Works on villa 12.
1. Block A. Installation of engineering systems. Electrical work, fastening clips, laying electrical cables. 2. Block A. Installation of plasterboard frame…
Block A 1. Facade work. Plastering the facade. 2. Installation of storm drainage. Covering storm drainage boxes. 3. Finishing work. Laying porcelain tiles on…
1. Installation of engineering systems. — Electrical work. — Installation of fire extinguishing system. — Sealing of ventilation openings. 2. Plastering works…
1. Monolithic works. — Preparation of column formwork for installation. — Reinforcement of floor slabs, villas 15–16.
1. Block A. Installation of engineering systems. Electrical installation work, fastening clips, laying electrical cables. 2. Block A. Installation of…
Block A 1. Facade work. Plastering the facade. 2. Installation of storm drainage. Covering storm drainage boxes. Block B 1. Plastering work. Plastering the…
1. Installation of engineering systems. — Electrical work, 13th and 14th floors. — Installation of fire extinguishing system, floors 6–20. — Sealing of…
1. Monolithic works. Formwork installation for floor slabs, villas 15–16.
1. Block A. Installation of engineering systems. Electrical work, fastening clips, pulling electrical cables. 2. Block A. Installation of plasterboard frame…
Block A 1. Facade work. Cladding the facade with clinker tiles, on the roof. 2. Plastering work. Installation of decorative plaster on balconies. 3. Finishing…
1. Installation of engineering systems. — Electrical work, installation of clips, laying of electrical cables, 14th floor. — Installation of fire extinguishing…
1. Monolithic works. — Installation of staircase formwork, villa 1. — Installation of columns, villa 15–16. 2. Installation of stained glass structures and…
1. Block A. Installation of engineering systems. Electrical installation work, fastening clips, pulling electrical cables. 2. Block C. Installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st