1. Continuation of column reinforcement, Villa 8. This ensures the strength and stability of the columns, preventing deformation and increasing the durability…
Construction progress, complex updates and real estate investment news from Batumi
1. Continuation of column reinforcement, Villa 8. This ensures the strength and stability of the columns, preventing deformation and increasing the durability…
— 1. Ceramic block installation. Block B on the 2nd floor, Block C on the 3rd floor. The ceramic blocks are being laid in accordance with the established…
— Building A 1. Installation of ledges for stained glass, the 4th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained…
1. Diamond drilling for engineering openings Layout and drilling are underway, necessary for future hotel utility installations. 2. Mock-up construction This…
— 1. Completion of formwork installation for the ceiling slab, Villas 2, 6 This is necessary for shaping and supporting the concrete during pouring, ensuring…
— 1. Ceramic block installation. Block B on the 2nd floor, Block C on the 3rd floor The ceramic blocks are being laid in accordance with the established…
Building A 1. Installation of ledges for stained glass, the 4th floor The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, 14th – 16th floors Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Floor tiling, units on the 3rd residential floor Surface leveling and tile installation with adherence to joints and required standards to ensure durability…
1. Continuation of slab formwork installation, Villas 2 and 6 This step creates the necessary form and support for concrete pouring, ensuring the precise…
1. Ceramic block installation. Block B on the 3rd floor, Block C on the 2nd floor, Block E on the 3rd floor The ceramic blocks are being laid in accordance with…
1. Diamond drilling for engineering openings Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained…
Building A 1. Installation of ledges for stained glass, the 4th floor The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Floor tiling, units on the 3rd residential floor Surface leveling and tile installation with adherence to joints and required standards to ensure durability…
1. Continuation of slab formwork installation, Villas 1 and 4 This step creates the necessary form and support for concrete pouring, ensuring the precise…
1. Ceramic block installation. Block B on the 3rd floor, Block C on the 2nd floor, Block E on the 3rd floor The ceramic blocks are being laid in accordance with…
1. Installation of ledges for stained glass, the 4th floor The formwork is installed, the concrete is poured, and compacted. After the concrete hardens, the…
1. Diamond drilling for engineering openings Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained…
1. diamond drilling of engineering holes The marking and drilling is carried out, which is necessary for the installation of communications of the future hotel…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st