— 1. Ceramic block installation. Block C on the 1st and 3rd floors. The ceramic blocks are being laid in accordance with the established standards. This process…
Construction progress, complex updates and real estate investment news from Batumi
— 1. Ceramic block installation. Block C on the 1st and 3rd floors. The ceramic blocks are being laid in accordance with the established standards. This process…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, the 19th - 20th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Painting is underway. 2. Cladding ceramic granite in the bathrooms…
1. Continuation of column formwork installation, Villas 8, 9. Column formwork is installed to shape and hold the concrete structure until it hardens. 2…
1. Ceramic block installation. Block C on the 2nd and 3rd floors. The ceramic blocks are being laid in accordance with the established standards. This process…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, the 19th - 20th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Painting is ongoing. 2. Cladding ceramic granite in the bathrooms…
Due to adverse weather conditions, the construction work on the site is not being carried out today.
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained…
1. Continuation of column formwork installation, Villa 8. Column formwork is installed to shape and hold the concrete structure until it hardens. 2…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, the 10th,17th floors. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Finishing works are ongoing. 2. Cladding ceramic granite in the…
Due to adverse weather conditions the construction work at the site is not being carried out today.
1. Ceramic block installation. Block C on the 1st and 3rd floors. The ceramic blocks are being laid in accordance with the established standards. This process…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, the 9th floor. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st