1. Continuation of column reinforcement, Villas 8 and 9. It ensures the strength and stability of the columns, preventing deformation and enhancing the…
Construction progress, complex updates and real estate investment news from Batumi
1. Continuation of column reinforcement, Villas 8 and 9. It ensures the strength and stability of the columns, preventing deformation and enhancing the…
1. Ceramic block installation. Block B on the 2nd floor, Block C on the 3rd floor. The ceramic blocks are being laid in accordance with the established…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, floors 10th, 17th. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Finishing works are ongoing. 2. Cladding ceramic granite in the…
1. Continuation of column reinforcement at Villa 8 and commencement of column reinforcement at Villa 9. It ensures the strength and stability of columns…
1. Ceramic block installation. Block B on the 2nd floor, Block C on the 3rd floor, Block A on the 1st floor, on the terrace. The ceramic blocks are being laid…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings, floors 16th -17th. Layout and drilling are underway, necessary for future hotel utility installations. 2…
1. Mock-up construction. This enables visualization and testing of design and materials. Finishing works are ongoing. 2. Cladding ceramic granite in the…
1. Concrete pouring of the floor slab, Villas 2, 6. This is essential to enhance the strength and stability of the structure, allowing the slab to withstand…
1. Ceramic block installation. Block B on the 2nd floor, Block C on the 3rd floor, Block A on the 1st floor, on the terrace. The ceramic blocks are being laid…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained…
1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Mock-up construction. This…
1. Continuation of column reinforcement, Villa 8. This ensures the strength and stability of the columns, preventing deformation and increasing the durability…
1. Ceramic block installation. Block B on the 2nd floor, Block C on the 3rd floor. The ceramic blocks are being laid in accordance with the established…
Building A 1. Installation of ledges for stained glass, the 5th floor. The formwork is installed, the concrete is poured, and compacted. After the concrete…
1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Installation of stained…
1. Diamond drilling for engineering openings. Layout and drilling are underway, necessary for future hotel utility installations. 2. Mock-up construction. This…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st