Block A 1. Installation of metal arches on balconies. — Installation of metal arches on balconies. — Painting of arches. 2. Facade works, 2nd floor. Facade…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Installation of metal arches on balconies. — Installation of metal arches on balconies. — Painting of arches. 2. Facade works, 2nd floor. Facade…
1. Installation of engineering systems. — Installation of power supply system, 20th floor. 2. Facade works. Plastering of the facade. 3. Gypsum plasterboard…
1. Finishing work. — Installation of baseboards, 5th floor. — Laying of porcelain tiles. — Installation of thresholds and porcelain stoneware, 5th floor…
1. Masonry works. Ceramic block masonry of the exterior walls of the 2nd floor, villa 11. 2. Installation of fireplaces, villa 6. Fireplaces masonry. 3…
1. Block A. Masonry works. Ceramoblock masonry on the technical floor 2. Block A. Facade works. Facade insulation, installation of mineral wool. 3. Block A…
Block A 1. Installation of metal arches on balconies. — Installation of metal arches on balconies. — Painting of arches. 2. Facade works, 2nd floor. Facade…
1. Installation of engineering systems. — Installation of electrical system, 20th floor. — Installation of water supply system, 2, 9th floor. 2. Facade works…
1. Finishing work. — Installation of moldings. — Laying porcelain stoneware. — Facing travertine on the balconies. — Painting works. 2. Facade works…
1. Masonry works. — Ceramoblock masonry external walls of the 1st floor, villa 11. — Ceramoblock masonry exterior walls of the 2nd floor, villa 11. 2…
1. Block A. Masonry works. Ceramoblock masonry on the technical floor 2. Block A. Manufacturing and installation of window sills. 3. Block B. Screeding…
Block A 1. Installation of metal arches on balconies. — Installation of metal arches on balconies. — Painting of arches. 2. Facade works. Arrangement of facade…
1. Facade works. — Plastering of the facade. — Facade insulation. 2. diamond drilling of engineering holes. For the device of engineering systems. 3…
1. Finishing work. — Installation of moldings. — Laying porcelain stoneware. — Facing travertine on the balconies. — Painting works. 2. Facade works…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 11. — Ceramoblock masonry exterior walls of the 2nd floor, villa 15, 16. 2…
1. Block A. Masonry works. Ceramoblock masonry on the technical floor 2. Block A. Manufacturing and installation of window sills. 3. Block E. Facade works…
Block A 1. Installation of metal arches on balconies. — Installation of metal arches on balconies. — Painting of arches. 2. Facade works. Arrangement of facade…
1. Installation of engineering systems. — Electricity supply system installation, 9th, 20th floor. — Plumbing works, 2–9 floors. 2. Facade works. Plastering of…
1. Finishing work. — Installation of moldings. — Laying porcelain stoneware. — Facing travertine on the balconies. — Painting works. 2. Facade works. Facing the…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 11, 12. — Ceramoblock masonry exterior walls of the 2nd floor, villa 11. 2…
1. Block A. Masonry works. Ceramoblock masonry on the stair parapet. 2. Block A. Dismantling of the formwork Works on the technical floor. 3. Block A…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st