Block A 1. Arrangement of metal arches on balconies. — Fabrication of metal arches to balconies. — Painting of arches. 2. Facade works. Facade insulation. Block…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Arrangement of metal arches on balconies. — Fabrication of metal arches to balconies. — Painting of arches. 2. Facade works. Facade insulation. Block…
1. Installation of engineering systems. — Electricity supply system installation, 9th, 19th, 20th floor. — Plumbing works, 2–9 floors. 2. Facade works…
1. Finishing work. — Installation of moldings. — Laying porcelain stoneware. — Facing travertine on the balconies. — Painting works. 2. Facade works. Facing the…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 12. 2. Installation of fireplaces, villa 6, 7, 8, 9, 10. Screed under the base of…
1. Block A. Masonry works. Ceramoblock masonry on the stair parapet. 2. Block A. Dismantling of formwork. Works on the technical floor. 3. Block A…
Block A 1. Arrangement of metal arches on balconies. — Fabrication of metal arches to balconies. — Painting of arches. Other construction works are not carried…
1. Installation of engineering systems. — Installation of electrical supply system, 20th floor. — Plumbing works. 2. Diamond drilling of engineering holes, 16th…
1. Finishing work. — Installation of moldings. — Laying porcelain stoneware. — Facing travertine on the balconies. — Painting works. 2. Facade works…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 12. — Ceramoblock masonry exterior walls of the 2nd and 3rd floors, villa 11. 2…
1. Block A. Screeding. Pouring of screed. 2. Block A. Installation of engineering systems. — Installation of hot and cold water supply system. 3. Block A…
Block A 1. Arrangement of metal arches on balconies. — Fabrication of metal arches to balconies. — Painting of arches. 2. Facade works. Arrangement of facade…
1. Installation of engineering systems. Installation of power supply system, 19th, 20th floor. 2. Diamond drilling of engineering holes, 16th floor. To install…
1. Finishing work. — Installation of moldings. — Laying porcelain stoneware. — Facing travertine on the balconies. 2. Facade works. — Plastering terraces…
1. Masonry works. Ceramoblock masonry of external walls of the 1st floor, villa 11, 12. 2. Concreting of monolithic floor slab II floor, villa 12, 13, 14…
1. Block A. Screeding. Pouring of screed. 2. Block A. Installation of engineering systems. — Installation of hot and cold water supply system. 3. Block A…
Block A 1. Arrangement of metal arches on balconies. Painting of arches. 2. Arrangement of stair shafts. — Preparation for installation of hinges. — Arrangement…
1. Installation of engineering systems. Installation of electrical supply system, 19th floor. 2. Plastering works. Plastering of balconies. 3. Diamond drilling…
1. Finishing work. — Installation of baseboards and moldings. — Painting baseboards, 4th floor. — Travertine trim on balconies. 2. Facade works. — Plastering of…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 11. — Ceramoblock masonry exterior walls of the 2nd floor, villa 9. 2…
1. Block A. Facade works. Facade insulation, installation of mineral wool. 2. Block A. Screeding. Pouring of screed on the terrace. 3. Block C. Installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st