Block A 1. Arrangement of metal arches on balconies. Painting of arches. 2. Plastering works, 2nd floor. Plastering of walls. Block B 1. Arrangement of curbs…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Arrangement of metal arches on balconies. Painting of arches. 2. Plastering works, 2nd floor. Plastering of walls. Block B 1. Arrangement of curbs…
1. Installation of engineering systems. Installation of power supply system, 19th, 20th floor. 2. Facade works. Plastering of the facade. 3. Plastering works…
1. finishing works. — Laying of porcelain stoneware skirting on terraces. — Painting in units, 5th floor. 2. Facade work. — Plastering of terraces parapets…
1. Masonry works. Ceramoblock masonry external walls of the 2nd floor, villa 9. 2. Installation of fireplaces, villa 1, 2, 4, 5. Masonry works. 3. Installation…
1. Block A. Installation of engineering systems. Installation of hot and cold water supply system. 2. Block A. Fabrication and installation of brackets for…
Block A 1. Facade works. Insulation of the facade. 2. Arrangement of metal arches on balconies. — Manufacturing and installation of arches. — Painting of…
1. Installation of engineering systems. Installation of power supply system, 20th floor. 2. Facade works. Plastering of the facade. 3. Plastering works…
1. finishing works. — Laying of porcelain stoneware skirting on the terraces. — Painting in units, 5th floor. 2. Facade work. — Plastering of terraces parapets…
1. Masonry works. Ceramoblock masonry exterior walls of the 2nd floor, villa 9. 2. Installation of fireplaces, villa 1, 2, 4, 5. Masonry works. 3. Arrangement…
1. Block A. Installation of engineering systems. Installation of hot and cold water supply system. 2. Block A. Plasterboard frame installation works…
Block A 1. Facade works. Facade insulation, installation of mineral wool. 2. Arrangement of metal arches on balconies. — Manufacturing and installation of…
1. Installation of engineering systems. Installation of power supply system, 20th floor. 2. Facade works. Plastering of the facade. 3. finishing works, 2, 3…
1. finishing works. — Laying of porcelain stoneware skirting on the terraces. — Painting in units, 5th floor. 2. Facade work. — Plastering of terraces parapets…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 9. — Ceramoblock masonry external walls of the 2nd floor, villa 8, 9, 10. 2…
1. Block A. Installation of engineering systems. Installation of hot and cold water supply system. 2. Block A. Plasterboard frame installation works…
Block A 1. Facade works, 3rd floor. Insulation of the facade, installation of mineral wool. 2. Ceiling installation. On the balconies of the 4th floor. 3…
1. Installation of engineering systems. Installation of power supply system, 20th floor. 2. Facade works. Plastering of the facade. 3. finishing works, 2, 3…
1. finishing works. — Laying of porcelain stoneware skirting on terraces. — Painting in units, 5th floor. 2. Facade work. — Plastering of terraces parapets…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 9. — Ceramoblock masonry external walls of the 2nd floor, villa 7, 8, 9, 10. 2…
1. Block A. Installation of engineering systems. — Installation of hot and cold water supply system. — Installation of storm water drainage system. 2. Block A…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st