Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. 2. Facade arrangement. Works on the device of facade…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. 2. Facade arrangement. Works on the device of facade…
1. Installation of engineering systems. Installation of electrical system, 12th floor. 2. Facade works. Insulation of the facade on balconies, 12–14 floors. 3…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of balconies with travertine. 2…
1. Masonry works. Ceramoblock masonry external walls, villa 3, 5, 6, 7.
1. Block A. Plastering works. Plastering of internal walls. 2. Block E. Installation of engineering systems. Installation of hot and cold water supply system.
Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. Block B 1. Plastering works. Plastering of roof parapets.
1. Installation of engineering systems. Electricity supply system installation, 12th floor. 2. finishing works, 3rd floor. Laying of ceramic tiles on balconies…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of balconies with travertine. 2…
1. Masonry works. Masonry exterior walls of ceramic block, villas 1, 3, 5, 6. 2. Concrete maintenance — Monolithic floor slab of the 2nd floor, villa 10, 11…
1. Block A. Installation of engineering systems. Electrical installation works. 2. Block A. Plastering works. Plastering of internal walls. 3. Block E…
Block A 1. Plastering works, 2nd floor. Plastering of internal walls. 2. Floor screeding works. Preparatory works and acceptance of materials. 3. Arrangement of…
1. Installation of engineering systems. Installation of electrical system, 12th floor. 2. Waterproofing works, 2nd, 7th floor. Work on the second layer of…
1- Finishing work. — Painting works in the units, 5th floor. — Laying of porcelain tiles on balconies and terraces. — Painting works on the staircase. — Facing…
1. Masonry works. Ceramoblock masonry exterior walls, villa 1, 3, 5, 6. 2. Concrete maintenance — monolithic floor slab II floor, villa 10, 11. — Monolithic…
1. Block A. Installation of engineering systems. Plumbing works. 2. Block A. Plastering works. Plastering of internal walls. 3. Block B. Plasterboard frame…
Block A 1. Facade arrangement. Works on facade insulation on balconies. 2. Plastering works, 2nd floor. Plastering of internal walls. 3. Floor screeding works…
1. Installation of engineering systems. — Installation of electricity supply system, 12th floor. — Installation of water supply system, 7th, 19th floor. 2…
1- Finishing work. — Painting works in units, 2nd, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of balconies with travertine. 2…
1. Masonry works. Ceramoblock masonry exterior walls, villa 1, 3, 5, 6. 2. Formwork for the monolithic staircase from 1 to 2 floors, villas 14, 15, 16…
1. Block A. Installation of engineering systems. Plumbing works. 2. Block A. Plastering works. Plastering of internal walls. 3. Block B. Plasterboard frame…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st