Block A 1. Facade works. Insulation of the facade. 2. Installation of suspended ceilings. Arrangement of ceiling framework on balconies. 3. Manufacturing of…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Facade works. Insulation of the facade. 2. Installation of suspended ceilings. Arrangement of ceiling framework on balconies. 3. Manufacturing of…
1. Installation of engineering systems. — Installation of electrical supply system, 3, 11 floors. — Arrangement of hot and cold water supply system, 3–9 floors…
1- Finishing work. — Painting in units, 5th floor. — Painting works in the common areas. — Laying of porcelain tiles on balconies and terraces. — Puttying of…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 6, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 3, 5. 2…
1. Block A. Installation of engineering systems. Installation of storm water drainage risers. 2. Block A. Installation of wall formwork, technical floor. 3…
Block A 1. Installation of stained glass windows, 3rd, 5th floor. Installation of stained glass structures and glass. 2. Installation of suspended ceilings, 1…
1. Installation of engineering systems. — Installation of electrical supply system, 11th floor. — Installation of hot and cold water supply system, 13, 15…
1- Finishing work. — Painting works in units, 5th floor. — Painting works in the common areas. — Laying porcelain tiles on balconies and terraces. — Facing of…
1. Masonry works. — Ceramoblock masonry external walls of the 1st floor, villa 6, 7. 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 3, 5…
1. Block A. Installation of engineering systems. — Installation of hot and cold water supply system. — Installation of heating system. 2. Block A. Formwork…
Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. 2. Arrangement of suspended ceilings, 1 floor. Arrangement…
1. Installation of engineering systems. — Installation of electrical system, 11th floor. — Installation of water supply system, 14th to 15th floor. 2. Facade…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of balconies with travertine. 2…
1. Masonry works. — Ceramoblock masonry exterior walls, villa 3, 5, 7. — Masonry on roof parapet, villa 1. 2. Dismantling of the staircase formwork from the 1st…
1. Block A. Plastering works. Plastering of internal walls. 2. Block E. Installation of engineering systems. — Installation of hot and cold water supply system…
Block A 1. Installation of stained glass windows. Installation of stained glass structures and glass. 2. Facade arrangement. Works on the device of facade…
1. Installation of engineering systems. Installation of electrical system, 11th floor. 2. Facade works. — Facade insulation on balconies, 12–14 floors…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of balconies with travertine. 2…
1. Masonry works. — Ceramoblock masonry exterior walls, villa 3, 5, 7. — Masonry on roof parapet, villa 1. 2. Dismantling of the staircase formwork from the 1st…
1. Block A. Plastering works. Plastering of internal walls. 2. Block E. Installation of engineering systems. — Installation of hot and cold water supply system…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st