Block A 1. Installation of engineering systems, 2nd floor. Installation of storm water drainage box frame. 2. Installation of stained glass structures…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Installation of engineering systems, 2nd floor. Installation of storm water drainage box frame. 2. Installation of stained glass structures…
1. Installation of engineering systems. — Installation of power supply system, 9th floor. — Installation of water supply system, 3–7 floors. 2. Facade works…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Installation of moldings. — Grouting of tiles…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 7, 8, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 6, 7…
1. Block A. Installation of engineering systems. Installation of hot and cold water supply system. 2. Block A. Dismantling of wall formwork, technical floor. 3…
Block A 1. Installation of engineering systems, 2nd floor. Installation of storm water drainage box frame. 2. Installation of stained glass structures…
1. Installation of engineering systems. — Installation of electrical supply system, 11th floor. — Installation of hot and cold water supply system, 6–7 floors…
1- Finishing work. — Painting works in units, 5th floor. — Painting works in the common areas. — Laying of porcelain tiles on balconies and terraces…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 7, 8, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 6. 2…
1. Block A. Installation of engineering systems. Installation of hot and cold water supply system. 2. Block A. Installation of wall formwork, technical floor…
Block A 1. Installation of engineering systems, 2–3 floor. Arrangement of storm water drainage box frame. 2. Installation of stained glass structures…
1. Installation of engineering systems. — Installation of electrical system, 11th floor. 2. Facade works. — Insulation of the facade on balconies, 5th floor…
1- Finishing work. — Painting works in units, 5th floor. — Painting works in the common areas. — Laying of porcelain tiles on balconies and terraces…
1. Masonry works. — Ceramoblock masonry external walls of the 1st floor, villa 7, 10. — Ceramoblock masonry exterior walls of the 2nd floor, villa 6. 2…
1. Block A. Installation of engineering systems. Installation of hot and cold water supply system. 2. Block A. Installation of wall formwork, technical floor…
Block A 1. Installation of engineering systems, 2–3 floor. Installation of storm water drainage box frame. Block B 1. Plastering works. Plastering of walls on…
1. Installation of engineering systems. — Installation of power supply system, 9th floor. — Installation of water supply system, 8–9 floors. 2. Facade works…
1- Finishing work. — Painting works in units, 5th floor. — Painting works in the common areas. — Laying of porcelain tiles on balconies and terraces. — Puttying…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 6, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 5. 2…
1. Block A. Installation of engineering systems. — Electrical installation works. — Installation of storm water drainage. 2. Block A. Installation of wall…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st