Block A 1. Facade arrangement. Works on facade insulation on balconies. 2. Plastering works, 2nd floor. Plastering of internal walls. 3. Floor screeding works…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Facade arrangement. Works on facade insulation on balconies. 2. Plastering works, 2nd floor. Plastering of internal walls. 3. Floor screeding works…
1. Installation of engineering systems. — Installation of electrical system, 12th floor. — Installation of water supply system, 3, 9th floor. 2. Facade works…
1. Finishing Work. — Painting works in units, 2nd, 5th floor. — Laying of porcelain tiles on balconies and terraces. — Facing of vestibules with travertine. 2…
1. Masonry works. Ceramoblock masonry external walls, villa 1. 2. Formwork for the monolithic staircase from 1st to 2nd floor, villas 12. Installation of…
1. Block A. Installation of engineering systems. — Fabrication of boxes for storm water drainage. — Plumbing works. 2. Block A. Formwork fabrication and casting…
Block A 1. Facade construction. Works on facade insulation on balconies. 2. Floor screed works. Preparation works. 3. Arrangement of the framework of ceilings…
1. Installation of engineering systems. Installation of electrical system, 12th floor. 2. Facade works. — Insulation of the facade on balconies, 11th, 13th…
1. Finishing work. — Painting works in units, 2nd, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of vestibules with travertine. 2…
1. Masonry works. Ceramoblock masonry external walls, villa 1. 2. Dismantling of the formwork of the floor slab of the second floor, villa 9. Removal of…
1. Block A. Installation of engineering systems. — Electrical installation works. — Installation of storm water drainage. 2. Block B. Plasterboard frame…
Block A 1. Facade arrangement. Works on facade insulation on balconies. 2. Floor screed works. Preparation works. 3. Arrangement of the framework of ceilings on…
1. Installation of engineering systems. Installation of electrical system, 16th floor. 2. Facade works. Insulation of the facade on balconies, 11, 13, 16…
1- Finishing work. — Painting works in units, 2nd, 5th floor. — Laying porcelain tiles on balconies and terraces. — Facing of vestibules with travertine. 2…
1. Masonry works. Ceramoblock masonry exterior walls, villa 1. 2. Formwork — Columns II floor, villa 14. — Monolithic staircase from 1 to 2 floors, villas 11…
1. Block A. Plastering works. Plastering of internal walls. 2. Block A. Installation of engineering systems. Electrical installation works. 3. Block A…
Block A 1. Facade arrangement. Works on facade insulation on balconies. 2. Floor screed works. Preparatory works. 3. Arrangement of the framework of ceilings on…
1. Installation of engineering systems. Installation of electrical system, 16th-17th floor. 2. Facade works. Facade insulation on balconies, 11th, 13th, 14th…
1. finishing works. — Painting works in units, 2nd, 5th floor. — Laying porcelain tiles on balconies and terraces. — Painting works on the staircase. 2…
1. Masonry works. Ceramoblock masonry exterior walls, villa 1, 2. 2. Dismantling of the formwork of the floor slab II floor, villa 8, 9. Removal of formwork…
1. Block A. Plastering works. Plastering of internal walls. 2. Block A. Installation of engineering systems. Electrical and plumbing work. 3. Block B…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st