Block A 1. Facade construction. Works on facade insulation and partition walls on balconies. 2. Plastering works, 5th floor. Plastering of internal walls. 3…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Facade construction. Works on facade insulation and partition walls on balconies. 2. Plastering works, 5th floor. Plastering of internal walls. 3…
1. Installation of engineering systems. — Installation of power supply system, 16–18, 20 floors. — Installation of ventilation system, 17–18 floors. 2. Facade…
1. Finishing work. — Painting works in units, 2nd, 5th floor. — Laying of porcelain tiles on balconies and terraces. 2. Waterproofing works. On the balconies…
1. Masonry works. Ceramoblock masonry exterior walls, villa 1, 2, 3. 2. Formwork — Columns II floor, villa 12, 13, 14. — Floor slabs II floor, villa 10, N11…
1. Block A. Installation of chimney pipe frames. 2. Block A. Installation of engineering systems. Electrical and plumbing work. 3. Block A. Masonry works…
Block A 1. Facade construction. — Works on facade insulation and partition walls on balconies. — Plastering of walls on balconies, 1, 4 floors. 2. Plastering…
1. Installation of engineering systems. Installation of ventilation system, 17th-18th floor. 2. Facade works. Insulation of facade on balconies, 4, 11, 13…
1. finishing works. — Painting works in units, 2nd, 5th floor. — Laying porcelain tiles on balconies. 2. Waterproofing works. On the balconies and terraces…
1. Masonry works. Ceramoblock masonry external walls, villa 2. 2. Dismantling of the formwork of the floor slab of the second floor, villa 1. Removal of…
1. Block A. Installation of formwork and reinforcement frames of contour walls, technical floor. 2. Block A. Installation of engineering systems. Electrical and…
Block A 1. Facade construction. — Works on facade insulation and partition walls on balconies. — Plastering of walls on balconies, 1, 4 floors. 2. Plastering…
1. Installation of engineering systems. Installation of ventilation system, 15th-20th floor. 2. Facade works. Insulation of the facade on balconies, 4, 11, 13…
1. Finishing works. — Painting works in units, 2nd, 5th floor. — Tile grouting in units, 5th floor. — Laying porcelain tiles on balconies. — Installation of…
1. Masonry works. Ceramoblock masonry external walls, villa 1, 3. 2. Dismantling of the formwork of the floor slab of the second floor, villa 1. Removal of…
1. Block A. Plastering works. Plastering of internal walls. 2. Block A. Masonry work. Ceramoblock masonry, technical floor. 3. Block A. Installation of…
Block A 1. Facade arrangement. Works on facade insulation and partition walls on balconies. 2. Plastering works, 2nd, 5th floor. Plastering of internal walls…
1. Installation of engineering systems. — Electrical installation works, 18th floor. — Installation of ventilation system, 15–17 floors. 2. Facade works. Facade…
1. Finishing works. — Painting works in units, 2nd, 5th floor. — Tile grouting in bathrooms, 5th floor. — Laying porcelain tile in vestibules. -Installation of…
1. Masonry works. Ceramoblock masonry external walls, villa 1, 2. 2. Fabrication of embedded parts. Other construction works are not carried out on site due to…
1. Block A. Plastering works. Plastering of internal walls. 2. Block A. Masonry works. Ceramoblock masonry, technical floor. 3. Block A. Installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st