Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of slopes, 4th floor. 2. Facade works. Arrangement of reinforcing layer on mineral…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of slopes, 4th floor. 2. Facade works. Arrangement of reinforcing layer on mineral…
1. Masonry works. Ceramoblock masonry internal walls, villa 16 2. Plastering works. Plastering of internal walls in the villas. 3. Arrangement of boards for…
1. Installation of engineering systems. — Installation of storm water drainage system, 9–11 floors. — Installation of sewerage, 14–15 floors. — Electrical…
Work is underway to prepare the complex for final handover. All major construction stages have been completed and final works are being carried out on the site.
1. Masonry works. Ceramoblock masonry internal walls, villa 16 2. Plastering works. Plastering of internal walls in the villas. 3. Arrangement of boards for…
1. Waterproofing works. — Preparatory work for the application of waterproofing on the terraces of the townhouses. — Preparation of backyards for waterproofing…
Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of soffits, 4th floor. 2. Facade works. Arrangement of reinforcing layer on mineral…
1. Installation of engineering systems. — Installation of storm water drainage system, 7–9 floors. — Installation of sewerage system, 15th floor. 2. Facade…
1. Block C, E. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Infrastructure building. Arrangement of ligature.
1. Arrangement of curbs for installation of stained glass structures. — Arrangement of reinforcing frame of curbs. — Arrangement of the formwork of curbs…
Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of soffits, 4th floor. 2. Arrangement of the ceiling frame. On the balconies in the…
1. Installation of engineering systems. — Installation of storm water drainage system, 2–5 floors. — Electrical installation works. — Installation of…
1. Masonry works, villa 16. Continuation of ceramic block masonry of internal walls. 2. Arrangement of curbs for installation of stained glass structures…
Work is underway to prepare the complex for final handover. All major construction stages have been completed and final works are being carried out on the site…
1. Block C, E. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Waterproofing works. — Preparatory work for…
Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of soffits, 4th floor. 2. Arrangement of door openings. Arrangement of profiles…
1. Installation of engineering systems. — Installation of storm water drainage, 2–5 floors. — Electrical installation, 15–17 floors. 2. Facade works. Facade…
Work is underway to prepare the complex for final handover. All major construction stages have been completed and final works are being carried out on the site…
1. Masonry works, villa 15. Continuation of ceramic block masonry of internal walls. 2. Arrangement of curbs for installation of stained glass structures…
1. Block C, E. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Block E. Drilling of engineering holes. For…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st