Block A 1. Plastering works, 5th floor. Plastering of internal walls. 2. Facade works. Facade insulation, mineral wool reinforcement layer. 3. Arrangement of…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Plastering works, 5th floor. Plastering of internal walls. 2. Facade works. Facade insulation, mineral wool reinforcement layer. 3. Arrangement of…
1. Installation of engineering systems. — Installation of electrical system, 17th floor. — Plumbing works, 11th, 18th floor. — Installation of storm water…
1- Finishing work. Travertine cladding on balconies. 2. Facade works. — Puttying of joints of decorative figures. — Painting of terraces and decorative…
1. Masonry works, villa 15. Ceramoblock masonry of external walls. 2. Arrangement of curbs for installation of stained glass structures. Arrangement of…
1. Block A. Facade works. — Facade insulation, installation of mineral wool. — Installation of slopes.
Block A 1. Plastering works, 2 floors. Plastering of internal walls. 2. Installation of engineering systems. Installation of storm water drainage system…
1. Installation of engineering systems. — Electricity supply system installation, 17th floor. — Plumbing works, 11–18 floors. — Installation of storm water…
1- Finishing work. Travertine cladding on balconies. 2. Facade works. — Puttying the joints of decorative figures. — Painting of terraces and decorative…
1. Masonry works, villa 15. Ceramoblock masonry of external walls. 2. Arrangement of curbs for installation of stained glass structures. Arrangement of…
1. Block A. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Block A. Masonry works. Ceramoblock masonry…
Block A 1. Plastering works, 2 floors. Plastering of internal walls. 2. Installation of engineering systems. Installation of storm water drainage, lining of…
1. Installation of engineering systems. — Electricity supply system installation, 16–18 floors. — Plumbing works, 14–18 floors. 2. Plasterboard frame…
1- Finishing work. Travertine cladding on balconies. 2. Facade works. — Puttying of joints of decorative figures. — Painting of terraces and decorative…
1. Masonry works. Ceramoblock masonry exterior walls, villa 14. 2. Arrangement of curbs for installation of stained glass structures. Arrangement of reinforcing…
1. Block A. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Block B, C. Arrangement of stained glass structures…
Block A 1. Facade works. Facade insulation, mineral wool reinforcement layer. 2. Ceiling works on the balconies. 3. Plastering works, 2 floors. Plastering of…
1. Installation of engineering systems. — Electricity supply system installation, 18–19 floor. — Plumbing works, 18th-19th floor. 2. Plasterboard frame…
1. finishing works. — Facing marble staircases. — Facing travertine on the balconies. 2. Facade works. — Puttying the joints of decorative figures. — Painting…
1. Masonry works. Ceramoblock masonry exterior walls, villa 14. 2. Dismantling of staircase formwork, villa 2, 4. Removal of formwork after concrete curing to…
1. Block A. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Block A. Masonry works. Ceramoblock masonry…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st