Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of slopes, 4th floor.
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of slopes, 4th floor.
1. Installation of engineering systems. Installation of storm water drainage system, 5th, 6th floor. 2. Installation of elevator shafts. Installation of…
Work is underway to prepare the complex for final handover. All major construction stages have been completed and final works are being carried out on the site…
1. Arrangement of curbs for installation of stained glass structures. — Arrangement of reinforcing frame of curbs. — Arrangement of the formwork of curbs…
1. Block A, B, C. Facade works. — Facade insulation, installation of mineral wool. — Installation of slopes. Other construction works are not carried out today…
Block A 1. Plastering works. — Plastering of walls, 5th floor. — Plastering of slopes, 4th floor. No other construction works are being carried out at the site…
1. Installation of engineering systems. Installation of storm water drainage system, 5th, 6th floor. No other construction works are being carried out on the…
Work is underway to prepare the complex for final handover. All major construction stages have been completed and final works are being carried out on the site…
1. Arrangement of curbs for installation of stained glass structures. — Arrangement of reinforcing frame of curbs. — Arrangement of the formwork of curbs…
1. Block A. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Block A. Masonry work. Ceramoblock masonry. 3. Block…
Block A 1. Plastering works, 2, 5 floors. — Plastering of walls, 5th floor. — Plastering of soffits, 4th floor. 2. Facade works. — Facade insulation, mineral…
1. Installation of engineering systems. — Plumbing works, on the roof. — Installation of storm water drainage. 2. Plastering works, 2–4, 9th floor. Plastering…
Work is underway to prepare the complex for final handover. All major construction stages have been completed and final works are being carried out on the site…
1. Masonry works, villa 15. Ceramoblock masonry of external walls. 2. Arrangement of curbs for installation of stained glass structures. — Arrangement of…
1. Block A. Facade works. — Facade insulation, installation of mineral wool. — Installation of soffits. 2. Block B. Facade works. — Facade insulation, mineral…
Block A 1. Plastering works, 2, 5 floors. Plastering of internal walls. 2. Facade works. Facade insulation, mineral wool reinforcement layer. Block B 1…
1. Installation of engineering systems. — Installation of electrical system, 17th floor. — Plumbing works, 17th floor. — Installation of storm water drainage…
1- Finishing work. Travertine cladding on balconies. 2. Facade works. — Puttying of joints of decorative figures. — Painting of terraces and decorative…
1. Masonry works, villa 15. Ceramoblock masonry external walls. 2. Arrangement of curbs for installation of stained glass structures. — Arrangement of…
1. Block C. Facade works. — Facade insulation, installation of mineral wool. — Installation of slopes.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st