1. Reinforcement of the columns, Villas 6, 7, 8. It ensures the strength and stability of the columns, preventing deformation and increasing the building’s…
Construction progress, complex updates and real estate investment news from Batumi
1. Reinforcement of the columns, Villas 6, 7, 8. It ensures the strength and stability of the columns, preventing deformation and increasing the building’s…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block B. Installation of staircases. Formwork installation for the inside…
Building A 1. Facade works, the 3rd floor. Plastering of outer walls. 2. Installation of drywall framing, on the 5th floor. Installation of guide frames for…
1. Facade works. — Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors. — Facade plastering, the 14th — 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting. — Puttying of walls, preparation for painting, the 4th, 5th floors. — Installation of moldings, the 2nd floor. 2. Facade works…
1. Reinforcement of columns, Villas 6, 7, 8. It ensures the strength and stability of the columns, preventing deformation and increasing the building’s…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block B. Installation of staircases. Formwork installation for the inside…
Building A 1. Facade works. Plastering of outer walls. 2. Installation of drywall framing, on the 5th floor. Installation of guide frames for drywall…
1. Facade works. — Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors. — Facade plastering, the 2nd — 20th floors. 2. Installation of utilities…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block E. Facade works. — Facade plastering. 3. Block B. Installation of…
1. Finishing works. — Painting. — Puttying of walls, preparation for painting, the 4th, 5th floors. — Installation of moldings, the 2nd floor. 2. Facade works…
1. Reinforcement of columns, Villas 6, 7. It ensures the strength and stability of the columns, preventing deformation and increasing the building’s durability…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the ledges on the balconies. 2. Installation of drywall framing…
1. Facade works. — Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors. — Facade plastering, the 2nd — 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting. — Puttying of walls, preparation for painting, the 4th, 5th floors. — Installation of moldings, the 2nd floor. 2. Facade works…
1. Reinforcement of columns, Villa 6, 7. It ensures the strength and stability of the columns, preventing deformation and increasing the building’s durability…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block A. Facade works. — Facade plastering. 3. Block B. Installation of…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the ledges on the balconies, the 3rd floor. — Cast-in place…
1. Facade works. — Facade winterization, the 4th, 7th,11th, 20th floors. — Façade plastering, the 2nd — 20th floors. 2. Installation of utilities systems…
1. Finishing works. — Painting. — Painting in the units, the 4th, 5th floors. — Installation of moldings, the 2nd floor. 2. Facade works. — Cladding the facade…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st