1. Installation of safety bars for the floor slabs, Villas 13, 16. 2. Construction of the fence. — Formwork removal from the fence lintel and posts No other…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of safety bars for the floor slabs, Villas 13, 16. 2. Construction of the fence. — Formwork removal from the fence lintel and posts No other…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block E. Facade works. — Facade plastering. 3. Block B. Installation of…
Building A 1. Installation of cast-in ledges on the balconies. — The installation of the reinforced frame for the balcony ledges. 2. Plastering on the 3rd…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of utilities systems…
1. Finishing works. — Painting. — Coating on the 4th floor. — Mable installation for the staircases, penthouses. — Installation of moldings, the 2nd floor…
1. Floor slab concreting, Villas 14.16. It creates a strong and level base for future floors, providing the necessary rigidity and resistance to loads 2…
1. Plastering. — Plastering of inner walls in Block E, the 1st- 3rd floors. 2. Block B. Staircases installation. — Pouring of inside staircases. 3. Block A…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges. 2. Plastering on the 1st- 4th floors…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th, 11th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting. — Puttying of the ceiling in the units, the 4th floor. — Puttying of the walls, penthouses. — Installation of moldings, the 4th…
1. Installation of formwork. — Floor slab, Villa 3. — Columns, Villas 2, 4, 5. — Staircases, Villas 1, 2. Formwork installation to create the necessary shape…
1. Plastering. — Plastering of inner walls in Blocks B, E. 2. Block B. Staircases installation. — Formwork installation for the staircases. 3. Block A. Masonry…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd, 5th floors. — Concreting the…
1. Facade works. — Facade winterization, the 5th, 7th, 11th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of utilities systems…
1. Finishing works. — Porcelain stoneware installation, the 1st- 5th floors. — Installation of wall porcelain stoneware in the bathrooms, the 5th floor…
1. Installation of formwork. — Floor slab, Villa 3. — Columns, Villas 2, 4. — Staircases, Villas 1, 2. Formwork installation to create the necessary shape for…
1. Plastering. — Plastering of inner walls in Block B. 2. Block B. Staircases installation. — Formwork installation for the staircases. — Concrete pouring for…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd, 5th floors. — Concreting the…
1. Facade works. — Facade winterization, the 5th, 7th, 11th floors. — Plastering of facade walls, the 4th — 20th floors. 2. Installation of utilities systems…
1. Finishing works. — Porcelain stoneware installation on the floor, the 1st- 5th floors. — Installation of wall porcelain stoneware in the bathrooms, the 5th…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st