1. Reinforcement of the: — Floor slabs of the II floor, Villa 4. — Staircases, Villa 3. It ensures the strength and stability of the structure, preventing…
Construction progress, complex updates and real estate investment news from Batumi
1. Reinforcement of the: — Floor slabs of the II floor, Villa 4. — Staircases, Villa 3. It ensures the strength and stability of the structure, preventing…
1. Plastering. — Plastering of inner walls in Block B, in Block A units 2 and 7. 2. Block B. Installation of staircases. Formwork installation for the inside…
Building A 1. Installation of the drywall framing, the 3rd floor. Installation of guide frames for drywall partitions, and the drywall frame construction. 2…
1. Installation of utilities systems. — Wiring, the 11th- 16th, 19th floors. — Installation of water piping, the 5th — 9th, 20th floors. — Installation of…
1. Finishing works. — Painting, the 4th floor and common areas. — Puttying of walls, preparation for painting, the 5th floor. — Installation of moldings. 2…
1. Reinforcement of the: — Columns of the II floor, Villa 9. — Floor slabs of the II floor. — Staircases, Villa 3. It ensures the strength and stability of the…
1. Plastering. — Plastering of inner walls in Block B, in Block A units 2 and 7. 2. Block B. Installation of staircases. Formwork installation for the inside…
Building A 1. Plastering, the 2nd, 3rd floors. Priming of internal walls for plastering. 2. Cast-in belt pouring for roof parapet. Building B. 1. Installation…
1. Facade works. — Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors. — Facade plastering, the 14th — 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting. — Puttying of walls, preparation for painting, the 4th, 5th floors. 2. Facade works. — Cladding the facade with natural stone…
1. Formwork Removal for Floor Slabs (2nd Floor), Villas 14, 16 After concrete has hardened it is required to remove the formwork to complete the structure and…
1. Plastering. — Plastering of inner walls in Blocks A, E, B the 1st- 3rd floors. 2. Block B. Installation of staircases. Formwork installation for the inside…
1. Facade works. — Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors. — Facade plastering, the 14th — 20th floors. 2. Installation of utilities…
Building A 1. Plastering, the 2nd, 3rd floors. Plastering of inner walls. 2. Installation of drywall framing, on the 1st floor. Installation of guide frames for…
1. Finishing works. — Painting. — Puttying of walls, preparation for painting, the 4th, 5th floors. — Installation of moldings, the 2nd floor. — Porcelain…
Due to weather conditions, no other construction work is underway at the site
1. Plastering. Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block B. Installation of staircases. Formwork installation for the inside…
Building A 1. Facade works, the 3rd floor. Plastering of inner walls. 2. Installation of drywall framing, on the 1st floor. Installation of guide frames for…
1. Facade works. — Facade winterization, the 2nd, 3rd, 6th, 7th,11th, 20th floors. — Facade plastering, the 14th — 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting. — Puttying of walls, preparation for painting, the 4th, 5th floors. — Installation of moldings, the 2nd floor. 2. Facade works…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st