1. Installation of safety bars for the floor slabs, Villa 16. 2. Construction of the fence. — Formwork removal from the fence lintel and post. — Ceramic block…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of safety bars for the floor slabs, Villa 16. 2. Construction of the fence. — Formwork removal from the fence lintel and post. — Ceramic block…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block A. Facade works. — Facade plastering. 3. Block B. Installation of…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the ledges on the balconies, the 3rd floor. — Cast-in place…
1. Facade works. — Facade winterization, the 2nd, 4th, 5th, 7th,12th, 20th floors. 2. Installation of utilities systems. — Wiring, the 17th floor…
1. Finishing works. — Painting. — Painting in the units, the 4th, 5th floors. — Installation of moldings, the 2nd floor. 2. Facade works. — Cladding the facade…
1. Dismantling of column formwork, Villa 2, 4, 5. Removal of formwork after concrete hardening to complete the structure and prepare for the next construction…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block A. Facade works. — Facade plastering. 3. Block B. Installation of…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the ledges on the balconies, the 3rd floor. — Cast-in place…
1. Facade works. — Facade winterization, the 2nd, 4th, 5th, 7th,12th, 20th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of…
1. Finishing works. — Painting. — Second coating, the 4th, 5th floors. — Mable installation for the staircases, penthouses. — Installation of moldings, the 2nd…
1. Installation of safety bars for the floor slabs, Villas 14, 16. 2. Construction of the fence. — Formwork removal from the fence lintel and posts. Due to…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block A. Facade works. — Facade plastering. 3. Block B. Installation of…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the ledges on the balconies, the 5th floor. — The installation of…
1. Facade works. — Facade winterization, the 2nd, 4th, 5th, 7th,11th, 20th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of…
1. Finishing works. — Painting. — Second coating, the 4th, 5th floors. — Mable installation for the staircases, penthouses. — Installation of moldings, the 2nd…
1. Removal of column formwork, Villas 2, 4, 5. Removal of formwork after the concrete has set to complete the structure and prepare for the next construction…
1. Plastering. — Plastering of inner walls in Blocks E, B the 1st- 3rd floors. 2. Block A. Facade works. — Facade plastering. 3. Block B. Installation of…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the ledges on the balconies, the 5th floor. — The installation of…
1. Facade works. — Facade winterization, the 2nd, 4th, 5th, 7th, 11th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting. — Second coating, the 4th floor. — Mable installation for the staircases, penthouses. — Installation of moldings, the 2nd floor…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st