Due to weather conditions, no other construction work is underway at the site.
Construction progress, complex updates and real estate investment news from Batumi
Due to weather conditions, no other construction work is underway at the site.
1. Building B. Construction of the staircases. Formwork installation for the inside stairs 2. Building C. Installation of stained glass windows. Installation of…
Building A 1. Installation of stained glass windows. Glazing and stained glass windows to be installed. Due to weather conditions, no other construction work is…
1. Installation of utilities systems. — Wiring, the 3rd, 16th, 19th floors. — Installation of water piping, the 17th floor. — Installation of exhaust…
1. Finishing works. — Painting, the 4th floor and common areas. — Installation of thresholds. Laying of porcelain stoneware on elevator portals. 2. Wiring…
Due to weather conditions, no other construction work is underway at the site.
1. Building B. Construction of the staircases. Formwork installation for the inside stairs 2. Building C. Installation of stained glass windows. Installation of…
Building A 1. Installation of stained glass windows. Glazing and stained glass windows to be installed. 2. Fabrication of hinges for elevator equipment…
1. Installation of utilities systems. — Wiring, the 3rd, 16th, 19th floors. — Installation of water piping, the 17th floor. — Installation of exhaust…
1. Finishing works. — Painting, the 4th floor and common areas. — Puttying of walls, preparation for painting, the 5th floor. 2. Wiring. Mounting of luminaires…
1. Installation of ladders for access to the floor slab Due to weather conditions, no other construction work is underway at the site.
1. Block B. Installation of staircases. Formwork installation for the inside staircases. 2. Block E. Installation of engineering systems. Installation of…
Building A 1. Installation of stained glass windows. Glazing and stained glass windows to be installed. 2. Fabrication of hinges for elevator equipment…
1. Installation of utilities systems. — Wiring, the 3rd, 16th, 19th floors. — Installation of water piping, the 17th floor. — Installation of exhaust…
1. Finishing works. — Painting, the 4th floor and common areas. — Puttying of walls, preparation for painting, the 5th floor. 2. Facade works. — Cladding the…
1. Installation of temporary bars for the slab of the 1st floor, Villas 14, 16. Due to weather conditions no other construction work is underway at the site.
1. Plastering. — Plastering of inner walls in Block B, in Block A units 2 and 7. 2. Block B. Installation of staircases. Formwork installation for the inside…
Building A 1. Plastering, the 3rd floor. Plastering of inside walls. 2. Installation of stained glass windows. Glazing and stained glass windows to be…
1. Installation of utilities systems. — Wiring, the 3rd, 19th floors. — Installation of water piping, the 5th, 20th floors. 2. Floor screeding. On the balconies…
1. Finishing works. — Painting, the 4th floor and common areas. — Puttying of walls, preparation for painting, the 5th floor. 2. Facade works. — Cladding the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st