1. Installation of formwork. — Floor slab, Villas 3. — Columns, Villas 2, 4. — Staircases, Villas 1, 2. Formwork installation to create the necessary shape for…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of formwork. — Floor slab, Villas 3. — Columns, Villas 2, 4. — Staircases, Villas 1, 2. Formwork installation to create the necessary shape for…
1. Plastering. — Plastering of inner walls in Block B. 2. Block B. Staircases installation. — Formwork installation for the staircases. — Concrete pouring for…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd, 5th floors. — Concreting the…
1. Facade works. — Facade winterization, the 5th, 7th, 11th floors. — Plastering of facade walls, the 2nd — 20th floors. 2. Installation of utilities systems…
1. Finishing works. — Porcelain stoneware installation, the 1st- 5th floors. — Installation of porcelain stoneware skirting board in the common areas…
1. Removal of column formwork, Villa 3. Removal of formwork after the concrete has set to complete the structure and prepare for the next construction stage. 2…
1. Plastering. — Plastering of inner walls in Blocks C, B. 2. Block B. Staircases installation. — Formwork installation for the staircases. — Concrete pouring…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd floor. — Concreting the ledges on…
1. Facade works. — Facade winterization, the 5th, 7th, 11th floors. — Plastering of facade walls, the 2nd- 20th floors. — Installation of balcony railings, the…
1. Finishing works. — Porcelain stoneware installation, the 4th floor. — Installation of porcelain stoneware skirting board in the common areas. — Puttying the…
1. Removal of column formwork, Villa 14, 16. Removal of formwork after the concrete has set to complete the structure and prepare for the next construction…
1. Plastering. — Plastering of inner walls in Blocks C, B. 2. Block B. Staircases installation. — Formwork installation for the staircases. — Concrete pouring…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd, 5th floors. — Concreting the…
1. Facade works. — Facade winterization, the 4th, 5th, 11th floors. — Plastering of facade walls, the 2nd- 20th floors. — Installation of balcony railings, the…
1. Finishing works. — Porcelain stoneware installation in common areas. — Installation of porcelain stoneware skirting board, the 1st, 2nd, 4th floors…
1. Concreting of the floor slab, Villa 13. It creates a strong and level base for future floors, providing the necessary stiffness and load resistance. 2…
1. Plastering. — Plastering of inner walls in Blocks C, B. 2. Block B. Ongoing formwork installation for staircases. It helps to create the exact shape and…
Building A 1. Installation of cast-in ledges on the balconies. — The formwork installation for the balcony ledges on the 3rd, 5th floors. — Concreting the…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th, 14th floors. — Plastering of facade walls, the 2nd- 20th floors. 2. Installation of utilities…
1. Finishing works. — Marble installation in penthouses. — Porcelain stoneware installation in common areas. — Grouting of porcelain stoneware flooring in…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st