1. Continuation of column reinforcement work, Villas 3 and 16. It ensures the strength and stability of the columns, preventing deformation and enhancing the…
Construction progress, complex updates and real estate investment news from Batumi
1. Continuation of column reinforcement work, Villas 3 and 16. It ensures the strength and stability of the columns, preventing deformation and enhancing the…
1. Plastering. — Plastering of inner walls in Blocks C, B. 2. Block B. Ongoing formwork installation for staircases. It helps to create the exact shape and…
Building A 1. Installation of cast-in ledges on the balconies. — The ledges are being reinforced on the balconies, the 4th floor. — Concreting the ledges on the…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th, 14th floors. — Plastering of facade walls, the 2nd- 20th floors. 2. Installation of utilities…
1. Finishing works. — Painting on the staircases and in the units, the 1st floor. — Porcelain stoneware installation in common areas, penthouses, the 5th floor…
1. Continuation of column reinforcement work, Villa 16. It ensures the strength and stability of the columns, preventing deformation and enhancing the…
1. Plastering. — Plastering of inner walls in Block C. 2. Block B. Ongoing formwork installation for staircases. It helps to create the exact shape and geometry…
Building A 1. Installation of cast-in ledges on the balconies. — The ledges are being reinforced on the balconies, the 3rd floor. — The ledges are being…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th, 14th floors. — Plastering of facade walls, the 2nd- 20th floors. 2. Installation of utilities…
Building A 1. Installation of cast-in ledges on the balconies. — The ledges are being reinforced on the balconies, the 3rd floor. — The ledges are being…
1. Finishing works. — Painting on the staircases and in the units, the 1st floor. — Porcelain stoneware installation in common areas, penthouses, the 5th floor…
1. Continuation of column reinforcement work, Villas 14, 16. It ensures the strength and stability of the columns, preventing deformation and enhancing the…
1. Plastering. — Plastering of inner walls in Block C on the 1st — 3rd floors. 2. Block B. Ongoing formwork installation for staircases. It helps to create the…
Building A 1. Installation of cast-in ledges on the balconies. — The ledges are being reinforced on the balconies, the 3rd floor. — The ledges are being…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th, 14th floors. — Plastering of facade walls, the 2nd- 20th floors. 2. Installation of utilities…
1. Finishing works. — Installation of the moldings, the 4th floor. — Painting on the staircases and in the units, the 1st floor. — Porcelain stoneware…
1. Removal of slab formwork, Villa 11. Removal of the formwork after the concrete has cured to complete the structure and prepare for the next construction…
1. Plastering. — Plastering of inner walls in Block C on the 1st — 3rd floors. 2. Block B. Ongoing formwork installation for staircases. It helps to create the…
Building A 1. Installation of cast-in ledges on the balconies. — The ledges are being reinforced on the balconies, the 3rd floor. — The ledges are being…
1. Facade works. — Facade winterization, the 3rd, 5th, 7th, 14th floors. — Plastering of facade walls, the 2nd- 20th floors. 2. Installation of utilities…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st