1. Finishing works. — Installation of moldings and skirting boards on the 2nd, 4th floors. — Puttying and plastering of walls and ceilings in the units, the…
Construction progress, complex updates and real estate investment news from Batumi
1. Finishing works. — Installation of moldings and skirting boards on the 2nd, 4th floors. — Puttying and plastering of walls and ceilings in the units, the…
1. Formwork removal from the slab, Villa 11. The formwork is stripped off after concrete hardening to complete the structure and prepare for the next…
1. Plastering. Plastering of inner walls in Blocks A on the 1st floor, B on the 3rd floor, C on the 2nd floor. 2. Block B. Ongoing formwork installation for…
Building A 1. Installation of cast-in ledges on the balconies, the 3rd- 4th floors. The ledges are being formworked and reinforced for stained glass windows to…
1. Facade works. — Facade winterization, the 5th, 7th, 14th floors. — Plastering of facade walls, the 2nd- 20th floors. 2. Installation of utilities systems…
1. Finishing works. — Marble facing of staircase steps. — Installation of moldings and skirting boards on the 2nd, 4th floors. — Puttying and plastering of…
1. Installation of the railings, Villa 12. Installation of slab guardrails. Due to weather conditions, no other construction work is underway at the site today.
1. Plastering. Plastering of inner walls in Blocks A on the 1st floor, B on the 3rd floor, C on the 2nd floor. 2. Block B. Ongoing formwork installation for…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Facade winterization, the 6th, 7th, 14th floors. 2. Installation of utilities systems. — Hot and cold water supply risers are being installed…
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Finishing works, on the 1st — 4th…
1. Installation of the railings, Villa 12. Installation of slab guardrails. Due to weather conditions, no other construction work is underway at the site today.
1. Plastering. Plastering of inner walls in Blocks A, B, E, C 2. Block B. Ongoing formwork installation for staircases. It helps to create the exact shape and…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Facade winterization, the 6th, 7th, 14th floors. 2. Installation of utilities systems. — Hot and cold water supply risers are being installed…
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Finishing works, on the 1st — 4th…
1. Installation of the railings, Villa 11. Installation of slab guardrails. 2. Installation of engineering openings, Villas 7, 11. Marking and drilling of…
1. Blocks A, C, E. Plastering. Plastering of inner walls. 2. Block B. Ongoing formwork installation for staircases. It helps to create the exact shape and…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Facade winterization, the 6th, 7th, 14th floors. 2. Installation of utilities systems. — Hot and cold water supply risers are being installed…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st