30.04.25

Elite Family Residence

1- Finishing work.
— Painting works in the units, 5th floor.
— Laying porcelain tiles on balconies and terraces.
— Installation of moldings.
— Grouting of tiles on terraces.

2. Facade works.
Facing with natural stone.

3. landscaping.
Facing with stone retaining wall.

4. Installation of railings of the central facade.

5. electrical installation works.

30.04.25

Wyndham Grand Batumi Gonio. Villas.

1. Masonry works.
— Ceramoblock masonry exterior walls of the 1st floor, villa 7, 8, 10.
— Ceramoblock masonry of external walls of the 2nd floor, villa 6, 7.

2. reinforcement of the floor slab, villa 10, 11.
Provides strength and stability to the structure, preventing deformation and increasing the durability of the building.

3. Arrangement of formwork for the floor slab II floor, villa 12.
Installation of formwork to create a mold, which is necessary for pouring concrete and forming the structure.

30.04.25

Wyndham Grand Batumi Gonio. Riviera.

1. Block A. Installation of engineering systems.
Installation of hot and cold water supply system.

2. Block A. Dismantling of wall formwork, technical floor.

3. Block B. Drilling of engineering holes.
For the device of engineering systems.

4. Block C. Screeding.
Pouring of screed on terraces.

5. Block E. Installation of engineering systems.
— Installation of air-conditioning system.
— Electrical installation works.

6. Fabrication and installation of storm water drainage boxes.

30.04.25

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Installation of engineering systems, 2nd floor.
Installation of storm water drainage box frame.

2. Installation of stained glass structures.
Installation of stained glass windows and glass.
3. Facade works.
Insulation of the facade.

4. Plastering works, 2nd floor.
Plastering of internal walls.

Block B
1. Work on the roof of the building.

30.04.25

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Installation of electrical supply system, 11th floor.
— Installation of hot and cold water supply system, 6–7 floors.

2. Facade works.
Plastering of the facade, 6, 8, 15, 19 floors.

3. Floor screed works.
On the 12th floor.

4. finishing works, 2 floor.
Laying ceramic tiles on the balconies.

5. Works on the installation of gypsum plasterboard frame, 12, 16 floors.

6. Arrangement of mocap, 3 floor.
Finishing works.

7. Works on the roof of the building.
— Manufacturing and installation of props.
— Drilling of engineering holes.

8. Works on the device of elevator shafts.
Plastering works.

9. Infrastructure building.
— Reinforcement of walls.
— Installation of formwork.

29.04.25

Elite Family Residence

1- Finishing work.
— Painting works in units, 5th floor.
— Painting works in the common areas.
— Laying of porcelain tiles on balconies and terraces.
— Installation of skirting boards.
— Facing of balconies with travertine.

2. Facade works.
Facing natural stone.

3. landscaping.
Facing the retaining wall with stone.