Block A 1. Facade works, 3rd floor. Insulation of the facade, installation of mineral wool. 2. Installation of engineering systems, 4th floor. Arrangement of…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Facade works, 3rd floor. Insulation of the facade, installation of mineral wool. 2. Installation of engineering systems, 4th floor. Arrangement of…
1. Installation of engineering systems. Installation of power supply system, 20th floor. 2. Facade works. — Insulation of the facade, 8–14 floors. — Plastering…
1. finishing works. — Laying porcelain stoneware on balconies. — Installation of moldings. — Laying of porcelain stoneware skirting on the terraces. — Painting…
1. Masonry works. — Ceramoblock masonry exterior walls 1 floor, villa 8, 9, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 7, 8, 10. 2…
1. Block A. Installation of engineering systems. — Electrical installation works. — Installation of air-conditioning system. — Hot and cold water supply system…
Block A 1. Facade works, 3rd floor. Insulation of the facade, installation of mineral wool. 2. Installation of engineering systems, 4th floor. Arrangement of…
1. Installation of engineering systems. — Installation of power supply system, 20th floor. — Installation of water supply system, 2nd floor. 2. Facade works…
1. finishing works. — Laying porcelain stoneware on balconies. — Installation of moldings. — Laying of porcelain stoneware skirting on the terraces. — Facing…
1. Installation of engineering systems. Installation of power supply system, 9th, 20th floor. 2. Facade works. — Insulation of the facade, 8–14 floors…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 8, 9, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 7, 8…
1. Block A. Installation of engineering systems. Installation of electrical system. 2. Block A. Installation of window sills. Fabrication and installation of…
Block A 1. Facade works, 3rd floor. Insulation of the facade, installation of mineral wool. 2. Arrangement of metal arches on balconies. — Manufacturing and…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Installation of moldings. — Grouting of tiles…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 7, 9, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 6, 7…
1. Block A. Installation of engineering systems. — Installation of hot and cold water supply and heating system. — Installation of air-conditioning system…
Block A 1. Installation of engineering systems, 2nd floor. Flashing of storm sewer ducts. 2. Ceiling installation. Arrangement of ceiling framework. 3…
1. Installation of engineering systems. — Installation of power supply system, 9th floor. — Installation of water supply system, 3–5 floors. — Installation of…
1- Finishing work. — Painting works in the units, 5th floor. — Laying porcelain tiles on balconies and terraces. — Installation of moldings. — Grouting of tiles…
1. Masonry works. — Ceramoblock masonry exterior walls of the 1st floor, villa 7, 10. — Ceramoblock masonry of external walls of the 2nd floor, villa 6, 7, 8…
1. Block A. Installation of engineering systems. — Installation of hot and cold water supply and heating system. — Installation of air-conditioning system…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st