1. Formwork installation for columns of the II floor, Villa 8. Installation of formwork to shape the columns, essential for concrete pouring and structural…
Construction progress, complex updates and real estate investment news from Batumi
1. Formwork installation for columns of the II floor, Villa 8. Installation of formwork to shape the columns, essential for concrete pouring and structural…
1. Plastering. Plastering of the walls inside the buildings A. 2. Block A. Installation of fireplaces. Installation of fireplace chimneys. 3. Block A. Masonry…
Block A. 1. Installation of the ledges for stained glass window installation. Installation of reinforced ledges on the balconies, the 1st floor. 2. Installation…
1. Installation of utilities systems. — Wiring, the 15th floor. — Installation of water supply system, the 5th,-7th, 12th, 18th floors. — Ventilation system…
1. Finishing works. — Painting, the 3rd, 5th floors. — Laying of porcelain stoneware on elevator portals. 2. Facade works. — Facade cladding with natural stone…
1. Formwork installation for columns of the II floor, Villa 8. Installation of formwork to shape the columns, essential for concrete pouring and structural…
1. Plastering. Plastering of the walls inside the buildings A and B. 2. Building B. Construction of the staircases. Formwork installation for and removal from…
Block A. 1. Installation of drywall framing. Installation of frame guides for drywall partitions. 2. Insulation. On the terraces. Block B. 1. Masonry works…
1. Installation of utilities systems. — Wiring, the 15th, 19th floors. — Installation of water supply system, the 4th, 5th, 14th, 18th floors. — Ventilation…
1. Finishing works. — Painting, the 3rd, 5th floors. — Laying of porcelain stoneware on elevator portals. — Marble cladding for the fire places, the 5th floor…
1. Formwork installation for columns of the II floor, Villa 8. Installation of formwork to shape the columns, essential for concrete pouring and structural…
1. Plastering. Plastering of the walls inside the buildings A and B. 2. Building B. Construction of the staircases. Formwork installation for and removal from…
Block A. 1. Installation of drywall framing. Installation of frame guides for drywall partitions. 2. Insulation. On the terraces. Block B. 1. Masonry works…
1. Installation of utilities systems. — Wiring, the 15th, 19th floors. — Installation of water supply system, the 4th, 5th, 14th, 18th floors. — Ventilation…
1. Finishing works. — Painting, the 1st, 3rd floors. — Laying of porcelain stoneware on elevator portals. — Marble cladding for the fire places, the 5th floor…
1. Formwork installation for floor slab, Villa 5. Installation of formwork to create the necessary shape for concrete pouring and structural formation. 2…
1. Plastering. Plastering of the walls inside the buildings A and B. 2. Building B. Construction of the staircases. Formwork installation for and removal from…
Block A. 1. Glazing and installation of stained glass windows. 2. Installation of drywall framing. Installation of frame guides for drywall partitions. Block B…
1. Installation of utilities systems. — Wiring, the 19th floor. — Installation of water supply system, the 6th -9th floors. — Ventilation system installation…
1. Finishing works. — Painting, the 1st, 3rd floors. — Laying of porcelain stoneware on elevator portals. — Marble cladding for the fire places, the 5th floor…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st