1. Reinforcement: — Staircases from the 1st to the 2nd floor, Villas 5, 6. It ensures the strength and stability of the structure, preventing deformation and…
Construction progress, complex updates and real estate investment news from Batumi
1. Reinforcement: — Staircases from the 1st to the 2nd floor, Villas 5, 6. It ensures the strength and stability of the structure, preventing deformation and…
1. Plastering. Plastering of the walls inside the buildings A. 2. Block E. Installation of the utilities. Plumbing — installation of sewage and air conditioning…
Block A. 1. Installation of the ledges for stained glass window installation. Installation of reinforced ledges on the balconies, the 1st floor. 2. Installation…
1. Installation of utilities systems. — Wiring, the 15th, 19th floors. — Installation of water supply system, piping layout for hot and cold water supply, the…
1. Finishing works. — Painting, the 1st, 3rd, 5th floors. — Laying of porcelain stoneware on elevator portals. — Laying of porcelain stoneware in units on the…
1. Reinforcement: — Staircases from the 1st to the 2nd floor, Villas 5, 6. — II floor columns, Villas 10, 11. It ensures the strength and stability of the…
1. Plastering. Plastering of the walls inside the buildings A. 2. Block E. Installation of the utilities. Plumbing — installation of sewage and air conditioning…
Block A. 1. Installation of the ledges for stained glass window installation. Installation of reinforced ledges on the balconies, the 1st floor. 2. Installation…
1. Installation of utilities systems. — Wiring, the 15th, 19th floors. — Installation of water supply system, piping layout for hot and cold water supply, the…
1. Finishing works. — Painting, the 3rd, 5th floors. — Laying of porcelain stoneware on elevator portals. — Laying of porcelain stoneware in units on the 5th…
1. Formwork removal from the I floor columns, Villa 15. Removal of formwork after concrete has hardened to complete the structure and prepare for the next stage…
1. Plastering. Plastering of the walls inside the buildings A. 2. Block A. Installation of fireplaces. Installation of fireplace chimneys. 3. Block A. Masonry…
Block A. 1. Installation of the ledges for stained glass window installation. Installation of reinforced ledges on the balconies, the 1st floor. 2. Installation…
1. Installation of utilities systems. — Wiring, the 15th floor. — Installation of water supply system, piping layout for hot and cold water supply, the 7th-9th…
1. Finishing works. — Painting, the 3rd, 5th floors. — Laying of porcelain stoneware on elevator portals. — Laying of porcelain stoneware in units on the 5th…
1. Formwork removal from the II floor columns, Villa 1. Removal of formwork after concrete has hardened to complete the structure and prepare for the next stage…
1. Plastering. Plastering of the walls inside the buildings A. 2. Block A. Installation of fireplaces. Installation of fireplace chimneys. 3. Block A. Masonry…
Block A. 1. Installation of the ledges for stained glass window installation. Installation of reinforced ledges on the balconies, the 1st floor. 2. Installation…
1. Installation of utilities systems. — Wiring, the 15th floor. — Installation of water supply system, piping layout for hot and cold water supply, the 6th-9th…
1. Finishing works. — Painting, the 3rd, 5th floors. — Laying of porcelain stoneware on elevator portals. — Laying of porcelain stoneware in units on the 5th…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st