1. Formwork installation for floor slab, Villa 5. Installation of formwork to create the necessary shape for concrete pouring and structural formation. 2…
Construction progress, complex updates and real estate investment news from Batumi
1. Formwork installation for floor slab, Villa 5. Installation of formwork to create the necessary shape for concrete pouring and structural formation. 2…
1. Plastering. Plastering of the walls inside the buildings A and B. 2. Building B. Construction of the staircases. Formwork installation for and removal from…
Block A. 1. Glazing and installation of stained glass windows. 2. Installation of drywall framing. Installation of frame guides for drywall partitions. 3…
1. Installation of utilities systems. — Wiring, the 19th floor. — Installation of water supply system, the 6th -9th, 15th floors. — Ventilation system…
1. Finishing works. — Painting, the 1st floor. — Laying of porcelain stoneware on elevator portals. — Marble cladding for the fire places, the 5th floor. 2…
1. Formwork installation for floor slab, Villa 5. Installation of formwork to create the necessary shape for concrete pouring and structural formation. 2…
1. Plastering. Plastering of the walls inside the buildings A and B. 2. Building B. Construction of the staircases. Formwork installation for and removal from…
Block A. 1. Glazing and installation of stained glass windows. 2. Installation of drywall framing. Installation of frame guides for drywall partitions.
1. Installation of utilities systems. — Wiring, the 3rd, 16th, 19th floors. — Installation of water supply system, the 6th -9th floors. 2. Facade works. The…
1. Finishing works. — Painting, the 3rd floor. -Laying of porcelain stoneware on elevator portals. 2. Installation of the railing. Due to weather conditions, no…
Due to weather conditions, no other construction work is underway at the site.
1. Plastering. Plastering of the walls inside the building A. 2. Building B. Construction of the staircases. Formwork installation for and removal from the…
Block A. 1. Installation of the ledges for stained glass windows. On the 2nd floor. 2. Glazing and installation of stained glass windows. Due to weather…
1. Installation of utilities systems. — Wiring, the 19th floor. — Installation of water supply system, the 6th -9th, 15th floors. — Installation of exhaust…
1. Finishing works. — Painting, the 3rd floor. — Installation of the thresholds. — Laying of porcelain stoneware on elevator portals. 2. Installation of the…
Due to weather conditions, no other construction work is underway at the site.
1. Plastering. Plastering of the walls inside the building A. 2. Building B. Construction of the staircases. Formwork installation for the inside stairs. 3…
1. Waterproofing. The terraces are getting ready for insulation installation. Due to weather conditions, no other construction work is underway at the site.
1. Installation of utilities systems. — Wiring, the 19th floor. — Installation of water supply system, the 16th -15th floors. — Installation of exhaust…
1. Finishing works. — Painting, the 4th floor and common areas. — Cladding the fire places with the marble. — Laying of porcelain stoneware on elevator portals…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st