1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Finishing works, on the 1st — 2nd…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Finishing works, on the 1st — 2nd…
1. Installation of the railings, Villa 11. Installation of slab guardrails. Due to weather conditions, no other construction work is underway at the site today.
1. Blocks A, C, E. Plastering. Plastering of inner walls. 2. Block B. Formwork installation for staircases. It helps to create the exact shape and geometry of…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Facade winterization, the 6th, 7th, 14th, 15th floors. 2. Installation of utilities systems. — Hot and cold water supply risers are being…
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Painting the 1st coat, on the 1st — 2nd…
1. Formwork removal from the floor slab, Villa 11. Removal of the formwork after the concrete has cured to complete the structure and prepare for the next stage…
1. Blocks A, C, E. Plastering. Plastering of inner walls. 2. Block B. Formwork installation for staircases. It helps to create the exact shape and geometry of…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. — Facade winterization, the 7th floor. 2. Installation of utilities systems. — Hot and…
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Finishing works on the 1st, 2nd floors…
1. Fencing. Installation of the fence posts. 2. Installation of the railings, Villa 9. Due to weather conditions, no other construction activities are being…
1. Blocks A, E, C. Plastering. Plastering of inner walls. 2. Block B. Formwork installation for staircases. It helps to create the exact shape and geometry of…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. 2. Installation of utilities systems. — Hot and cold water supply risers are being…
1. Installation of porcelain stoneware tiles, penthouses. — Continued porcelain stoneware tiling. 2. Finishing works. — Finishing works on the 1st, 2nd, 3rd…
1. Concreting of the slab, Villa 15. It creates a strong and level base for future floors, providing the necessary rigidity and resistance to loads. 2…
1. Blocks A, E, C. Plastering. Plastering of inner walls. 2. Infrastructure building. Ceramic block installation on the roof. 3. Block B. Pouring concrete on…
Building A 1. Installation of cast-in ledges on the balconies. The ledges are being formworked and reinforced for stained glass windows to be installed. 2…
1. Facade works. — Plastering of facade walls, on the 2nd — 20th floors. — Facade winterization, the 3rd — 7th, 12th -13th floors. 2. Installation of utilities…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st