1. Installation of Engineering Systems Electrical installation work, 13th floor. Installation of the water supply system, 11th-20th floors. Installation of the…
Construction progress, complex updates and real estate investment news from Batumi
1. Installation of Engineering Systems Electrical installation work, 13th floor. Installation of the water supply system, 11th-20th floors. Installation of the…
1. Formwork Installation for Stairs from 1st to 2nd Floor, Villa 10. Installation of formwork to create the shape required for concrete pouring and structure…
Block A 1. Plastering Works Plastering of interior walls, 3rd floor. 2. Installation of Glazing Structures Installation of stained-glass windows. 3. Masonry…
1. Finishing Works Painting works in units, 1st, 2nd floors. Painting works in common areas. Tile installation, 5th floor. Porcelain tile installation in…
1. Finishing Works Painting works in units, 1st, 2nd floors. Painting works in common areas. Tile installation, 5th floor. Porcelain tile installation in…
1. Formwork Installation for the Columns of the 2nd Floor, Villa 11. Installation of formwork to create the shape of columns required for concrete pouring and…
1. Block B. Plastering Works Plastering of interior walls. 2. Block A. Mock-up Works Electrical installation. 3. Block A. Installation of Engineering Systems…
Block A 1. Plastering Works Plastering of interior walls, 2nd, 3rd floors. 2. Installation of Glazing Structures Installation of stained-glass windows. 3. Works…
Installation of Engineering Systems Electrical installation work, 3rd, 20th floors. Installation of the water supply system, 3rd-9th floors. 2. Facade Works…
1. Finishing Works Painting works in units, 1st, 2nd floors. Painting works in common areas. Tile installation, 5th floor. Porcelain tile installation in…
1. Formwork Installation for the Monolithic Slab of the 2nd Floor, Villas 7, 8, 9. Installation of formwork to create the shape required for concrete pouring…
1. Block A, B. Plastering Works Plastering of interior walls. 2. Block A. Mock-up Works Electrical installation. 3. Block A. Installation of Engineering Systems…
Block A 1. Plastering Works Plastering of interior walls, 2nd, 3rd floors. 2. Masonry Works Partition masonry on the 4th floor. Masonry of ceramic block on the…
1. Installation of Engineering Systems Electrical installation work, 14th floor. Installation of the water supply system, 3rd-9th, 11th-20th floors…
1. Finishing Works Painting works in units, 1st, 2nd floors. Painting works in common areas. Tile installation, 5th floor. Porcelain tile installation in…
1. Formwork Installation for the Monolithic Slab of the 2nd Floor, Villas 7, 8, 9. Installation of formwork to create the shape required for concrete pouring…
1. Block A, B. Plastering Works Plastering of interior walls. 2. Block A. Formwork and Reinforcement Installation for Contour Walls Technical floor. 3. Block A…
Block A 1. Plastering Works Plastering of interior walls, 2nd, 3rd floors. 2. Masonry Works Partition masonry on the 2nd, 3rd floors. 3. Elevator Shaft Works…
1. Installation of Engineering Systems Electrical installation work, 14th floor. Installation of the water supply system, 3rd-9th floors. Installation of the…
1. Finishing works. — Painting in the units, the 1st, , 2nd floors. — Painting in the common areas. — Painting on the staircases. — Tiling in the bathrooms, the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st