1. Formwork installation for cast-in floor slab (2nd Floor), Villas 7, 8, 9 Installation of formwork to create the necessary shape for concrete pouring and…
Construction progress, complex updates and real estate investment news from Batumi
1. Formwork installation for cast-in floor slab (2nd Floor), Villas 7, 8, 9 Installation of formwork to create the necessary shape for concrete pouring and…
1. Block A. Plastering. Plastering of the walls inside. 2. Block A. Formwork installation and reinforcement of the perimeter walls, basement. 3. Block A. Mockup…
Block A. 1. Plastering. Plastering of the walls inside, the 3rd floor. 2. Masonry work. Installation of partitions on the 2nd, 3rd floors. 3. Elevator Shafts…
1. Installation of utilities systems. — Wiring, the 14th floor. — Installation of water supply system, the 3rd — 7th floors. 2. Facade works. — The facade…
1. Finishing works. — Painting, the 1st, , 2nd floors. — Painting on the staircases. — Tiling in the bathrooms, the 5th floor. 2. Facade works. Cladding with…
1. Installation of temporary bars on steel posts of the floor slab of the II floor, Villa 9. 2. Fabrication of embedded parts from steel angles. No other…
1. Block A. Plastering. Plastering of the walls inside. 2. Block A. Formwork installation and reinforcement of the perimeter walls, basement. 3. Block A. Mockup…
Block A. 1. Plastering. Plastering of the walls inside, the 3rd floor. 2. Installation of the ledges for stained glass windows. Formwork removal from the…
1. Installation of utilities systems. — Wiring, the 14th — 15th floors. — Installation of water supply system, the 16th — 19th floors. 2. Facade works. — The…
1. Finishing works. — Painting, the 1st, 3rd, 5th floors. — Tiling in the bathrooms, the 5th floor. 2. Facade works. Cladding with the natural stone. 3…
1. Formwork installation for the staircases from the 1st to 2nd floors, Villa 10. Installation of formwork to create the necessary shape for concrete pouring…
1. Block A. Plastering. Plastering of the walls inside. 2. Block A. Mockup installation. Wiring. 3. Block A. Installation of engineering systems. Plumbing. 4…
Block A. 1. Plastering. Plastering of the walls inside, the 3rd floor. 2. Installation of the stained glass windows. Glazing and stained glass window…
1. Installation of utilities systems. — Wiring, the 14th floor. — Installation of water supply system, the 13th — 15th floors. 2. Facade works. — The facade…
1. Finishing works. — Painting, the 3rd, 5th floors. — Tiling in the bathrooms, the 5th floor. 2. Facade works. Cladding with the natural stone. 3…
1. Formwork removal from the II floor slab, Villa 4. Removal of formwork after concrete has hardened to complete the structure and prepare for the next stage of…
1. Block A. Plastering. Plastering of the walls inside. 2. Block A. Mockup installation. Wiring. 3. Block A. Installation of engineering systems. Plumbing. 4…
Block A. 1. Plastering. Plastering of the walls inside, the 3rd floor. 2. Installation of the ledges for stained glass window installation. On the balconies…
1. Installation of utilities systems. — Wiring, the 15th floor. — Ventilation system installation, the 20th floor. — Installation of water supply system, the…
1. Finishing works. — Painting, the 1st, 3rd, 5th floors. — Tiling in the bathrooms, the 5th floor. 2. Waterproofing. — On the balconies. 3. Installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st