1. Masonry works, villa 2, 4. Ceramoblock masonry of external walls. 2. Dismantling of monolithic foundation of fence enclosure, villa 13. 14. Removal of…
Construction progress, complex updates and real estate investment news from Batumi
1. Masonry works, villa 2, 4. Ceramoblock masonry of external walls. 2. Dismantling of monolithic foundation of fence enclosure, villa 13. 14. Removal of…
1. Block B. Plastering works. Plastering of internal walls. 2. Block A. Installation of formwork and reinforcement frames for contour walls, technical floor. 3…
Block A 1. Facade arrangement. — Works on facade insulation and partition walls on balconies. — Plastering of the facade. 2. Installation of monolithic belt on…
1. Installation of engineering systems. Electrical installation works, 13, 20th floor. 2. Facade works. Facade insulation on balconies, 4, 6, 7, 11 floor. 3…
1. finishing works. — Painting works in units, 1st, 2nd floor. — Painting in common areas. — Laying of tiles, 5th floor. — Laying of porcelain tiles in the…
1. Masonry works, villa 2, 4. Ceramoblock masonry of external walls. 2. Works on dismantling of formwork — stairs from 1st to 2nd floor, villa 5, 8, 9…
1. Block B. Plastering works. Plastering of internal walls. 2. Block A. Installation of formwork and reinforcement frames for contour walls, technical floor. 3…
Block A 1. Facade arrangement. — Works on facade insulation and partition walls on balconies. — Plastering of the facade. 2. Installation of monolithic belt on…
1. Installation of engineering systems. — Electrical installation works, 13, 20th floor. — Sewerage installation, sealing of systems. — Hot and cold water…
1. finishing works. — Painting works in units, 1st, 2nd floor. — Painting works in common areas. — Laying of tiles, 5th floor. — Laying porcelain tiles in the…
1. Masonry works, villa 2. Ceramoblock masonry of external walls of the II floor. 2. Masonry works, villa 4. Ceramoblock masonry of external walls of the I…
1. Block B. Plastering works. Plastering of internal walls. 2. Block A. Installation of formwork and reinforcement frames for contour walls, technical floor. 3…
Block A 1. Facade construction. Works on facade insulation and partition walls on balconies. 2. Installation of monolithic belt on the roof parapet. 3…
1. Installation of engineering systems. Electrical installation works, 13, 20th floor. 2. Facade works. Facade insulation on balconies, 4, 6, 7, 11 floor. 3…
1. Finishing Works Painting works in units, 1st, 2nd floors. Painting works in common areas. Tile installation, 5th floor. Porcelain tile installation in…
1. Concrete Curing Monolithic stairs from 1st to 2nd floor, Villas 8, 9. Monolithic floor slab of the 2nd floor, Villas 1, 7, 8, 9. 2. Masonry Works, Villas 2…
1. Block B. Plastering Works Plastering of interior walls. 2. Block A. Formwork and Reinforcement of Contour Walls, Technical Floor. 3. Block A. Installation of…
Block A 1. Plastering Works Plastering of interior walls, 3rd floor. Plastering in ventilation shafts, on the roof. 2. Installation of Glazing Structures…
1. Installation of Engineering Systems Electrical installation work, 13th floor. Installation of the water supply system, 11th-20th floors. 2. Facade Works…
1. Block B. Plastering Works Plastering of interior walls. 2. Block A. Formwork and Reinforcement of Contour Walls, Technical Floor. 3. Block A. Installation of…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st