Block A 1. Facade arrangement. Works on facade insulation and partition walls on balconies. 2. Plastering works, 2nd, 5th floor. Plastering of internal walls…
Construction progress, complex updates and real estate investment news from Batumi
Block A 1. Facade arrangement. Works on facade insulation and partition walls on balconies. 2. Plastering works, 2nd, 5th floor. Plastering of internal walls…
1. Installation of engineering systems. Electrical installation works, 18th floor. 2. Facade works. Insulation of the facade on balconies, 4, 11, 13 floors. 3…
1. finishing works. — Painting in units, 2, 5th floor. — Tile grouting in bathrooms, 5th floor. — Laying of porcelain tiles in vestibules. 2. Facade works…
1. Masonry works. — Ceramoblock masonry external walls, villa 1. — Masonry work of roof parapet. 2. Reinforcement of the staircase from the 1st to the 2nd…
1. Block C. Plastering works. Plastering of internal walls. 2. Block A. Installation of formwork and reinforcement frames for contour walls, technical floor. 3…
Block A 1. Facade arrangement. — Works on facade insulation and partition walls on balconies. — Plastering of the facade. 2. Installation of monolithic belt on…
1. Installation of engineering systems. — Electrical installation works, 16th, 18th floor. — Installation of ventilation system, 11–20 floors. 2. Facade works…
1. Finishing works. — Painting works in units, 2, 5th floor. — Tile grouting in bathrooms, 5th floor. — Laying of porcelain tiles in vestibules. 2. Facade…
1. Masonry works, villa 1, 2, 4. Ceramoblock masonry of external walls. 2. Works on dismantling the formwork — floor slab II floor, villa 6, — columns II floor…
1. Block A. Installation of thermal insulation. On the terraces. 2. Block A. Installation of formwork and reinforcement frames of contour walls, technical…
Block A 1. Facade arrangement. — Works on facade insulation and partition walls on balconies. — Plastering of the facade. 2. Installation of monolithic belt on…
1. Installation of engineering systems. Electrical installation works, 17th-18th floor. 2. Facade works. Facade insulation on balconies, 4th, 11th, 13th floors…
Block A 1. Facade arrangement. — Works on facade insulation and partition walls on balconies. — Plastering of the facade. 2. Installation of monolithic belt on…
1. Installation of engineering systems. Electrical installation works, 13th floor. 2. Facade works. Insulation of the facade on balconies, 4, 6, 11 floor. 3…
1- Finishing work. — Painting works in units, 1st, 2nd floor. — Painting in common areas. — Laying of tiles, 5th floor. — Laying of porcelain tiles in the…
1. Masonry works, villa 2, 4. Ceramoblock masonry of external walls. 2. Works on dismantling of formwork — floor slab II floor, villa 6, — columns II floor…
1. Block B. Plastering works. Plastering of internal walls. 2. Block A. Installation of formwork and reinforcement frames for contour walls, technical floor. 3…
Block A 1. Facade arrangement. — Works on facade insulation and partition walls on balconies. — Plastering of the facade. 2. Installation of monolithic belt on…
1. Installation of engineering systems. Electrical installation works, 20th floor. 2. Facade works. Facade insulation on balconies, 4, 6, 11 floors. 3…
1. finishing works. — Painting works in units, 1st, 2nd floor. — Painting in common areas. — Laying of tiles, 5th floor. — Laying of porcelain tiles in the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st